The agencies’ answer
It depends. Assuming the requirements in Section 528 of the Act (42 U.S.C. 4104b) are met and the same lender made the first mortgage, then a new determination may not be necessary when the existing determination is not more than seven years old, there have been no map changes, and the determination was recorded on an SFHDF. If, however, a lender other than the one that made the first mortgage loan is making the junior lien loan, a new determination would be required because this lender would be deemed to be “making” a new loan.108 In either situation, the lender will need to determine whether the amount of insurance in effect is sufficient to cover the lesser of the combined outstanding principal balance of all loans (including the junior lien loan), the insurable value, or the maximum amount of coverage available on the improved real estate. This will hold true whether the subordinate lien loan is a home equity loan or some other type of junior lien loan.
Footnotes
- 12 CFR 22.3(a), 22.6(a) (OCC); 12 CFR 208.25(c)(1) and (f)(1) (Board); 12 CFR 339.3(a), 339.6(a) (FDIC); 12 CFR 614.4930(a), 614.4940(a) (FCA); and 12 CFR 760.3(a), 760.6(a) (NCUA).
Source
- Interagency Questions and Answers Regarding Flood Insurance, 87 FR 32826 (May 31, 2022), Federal Register. Published by the OCC, the Federal Reserve, the FDIC, the Farm Credit Administration and the NCUA.
- Other Security Interests 5 on the Federal Reserve’s page for the Q&As.
Text retrieved October 29, 2026.