Force placement, from the lapse to the refund.

Follow one commercial loan, Saltmarsh Brewing Co (fictional), whose flood policy has lapsed.

  • 9 steps, about two minutes
  • Nothing to fill in
  • Illustrative screens, fictional data

In short: When a flood policy lapses, FloodCaliber™ prepares the borrower notice, counts the 45 days from it, works out the amount to place for each building and tracks the refund of any overlap. Every case sits on one board, with what is late first.

Force placement, step by step

  1. FloodCaliber™ loan page for MCB-1137, Saltmarsh Brewing Co: no coverage in force, short by $500,000; the gauge shows 0 percent covered.
    Saltmarsh Brewing Co’s flood policy has lapsed: no coverage in force, $500,000 short.
  2. FloodCaliber™ what needs attention: notice sent to the borrower on November 10, 2026 by mailed letter; coverage due by December 25, 2026.
    The borrower is told by mail on November 10, and the 45 days start: coverage is due by December 25.
  3. FloodCaliber™ the amount to place: $500,000 for the primary structure, with none in force.
    The amount to place is worked out building by building: $500,000 for the brewery’s one building.
  4. FloodCaliber™ force placement: due December 25, 2026, overdue, with the button to record the force-placed policy.
    The 45 days ran out on December 25 with no coverage in place, so the bank must now buy it.
  5. FloodCaliber™ note for the insurance vendor: the building, the flood zone, the coverage to place and the day it must start.
    A note for the insurance vendor is ready: what to place, for which building, from which day.
  6. FloodCaliber™ the force-placed policy recorded: $500,000 from December 26, 2026, with $6,250 charged to the borrower through escrow.
    The placed policy is recorded: $500,000 from December 26, and the $6,250 premium charged to the borrower.
  7. FloodCaliber™ the borrower’s proof arrived on January 8, 2027: tell the insurer and refund the overlap by February 7, 2027.
    The borrower’s own proof arrived on January 8: tell the insurer and refund the overlap by February 7.
  8. FloodCaliber™ force placement board: every case with its next step, late ones first, and MCB-1137 in cancel and refund.
    Every case sits on one board, from the notice to the refund, with what is late first.
  9. Every lapse caught. Every deadline tracked.

    Notices prepared, the 45 days counted from the notice, the amount to place worked out per building and the overlap refunded, all on one board.

Read more about force placement

See it on loan files like yours.